Abstract
By studying the construction process of ground-connected wall slurry trenches in the rock-throwing reclamation areas, this paper explored the effects of such factors as trench section width, weight of the slurry trench, parameters of the rock-throwing layer, the reinforcement zone range of the trench wall, and grouting parameters on the stability of the trench wall and the disturbance of the surrounding strata. Meanwhile, it measured the deformation modulus of the grouting reinforcement zone by experiments, and obtained the shear strength parameters from empirical formulas. The ground deformation characteristics induced by the construction of ground-connected wall in rock-throwing reclamation areas under different grouting reinforcement schemes were calculated and analyzed via the finite element method. The calculation results indicate that the maximum lateral displacement of the soil on the trench wall occurs at 1/3 to 1/2 of the trench section depth. Reinforcing the surrounding strata of the trench wall via grouting can reduce the trench wall’s lateral deformation and surface settlement. Additionally, compared to single slurry reinforcement, the joint grouting of mortar and double liquid slurry is more conducive to trench wall stability. The decreases in the deformation modulus of the rock-throwing layer and width of the trench section are beneficial for reducing the lateral deformation of the soil on the trench wall. Under too much weight of mud, the horizontal displacement of the soil on the trench wall presents an “inverted S-shaped” curve with the increasing depth, which means that lateral deformation of the soil on the trench wall will occur near the bottom of the trench section.
Publication Date
1-18-2024
DOI
10.14048/j.issn.1671-2579.2023.06.001
First Page
1
Last Page
7
Submission Date
March 2025
Recommended Citation
Xiaohua, BAO; Jihao, PAN; Hongzhi, CUI; Bo, WAN; and Zhen, ZHOU
(2024)
"Analysis of stability of trench formation and effect of ground deformation of ground⁃connected wall in rock⁃throwing reclamation area,"
Journal of China & Foreign Highway: Vol. 43:
Iss.
6, Article 56.
DOI: 10.14048/j.issn.1671-2579.2023.06.001
Available at:
https://zwgl1980.csust.edu.cn/journal/vol43/iss6/56
Reference
[1] DING Y C, WANG J H. Numerical modeling of ground response during diaphragm wall construction[J]. Journal of Shanghai Jiaotong University (Science), 2008, 13(4): 385-390. [2] 丁勇春,程泽坤,王建华,等.地下连续墙施工力学性状数值分析[J].岩土工程学报,2012,34(S1):87‑92. DING Yongchun, CHENG Zekun, WANG Jianhua, et al. Numerical analysis of mechanical behavior of underground continuous wall construction [J]. Chinese Journal of Geotechnical Engineering, 2012, 34(S1): 87-92. [3] 秦会来, 李峰, 郭院成. 超深地连墙槽段施工的三维数值分析[J]. 岩土工程学报, 2013, 35(S2): 335-340. QIN Huilai, LI Feng, GUO Yuancheng. Three-dimensional numerical analysis of groove section construction of ultra-deep diaphragm wall[J]. Chinese Journal of Geotechnical Engineering, 2013, 35(S2): 335-340. [4] COMODROMOS E M, PAPADOPOULOU M C, KONSTANTINIDIS G K. Effects from diaphragm wall installation to surrounding soil and adjacent buildings[J]. Computers and Geotechnics, 2013, 53: 106-121. [5] 李慕涵.超深地下连续墙成槽施工过程三维数值分析[J].地下空间与工程学报,2016,12(S1):296‑301. LI Muhuan. Three-dimensional numerical analysis of slotting construction process of super-deep underground continuous wall [J]. Chinese Journal of Underground Space and Engineering, 2016, 12(S1): 296-301. [6] 朱宁,周洋,刘维,等.苏州粉土地层地连墙施工对地层扰动影响研究[J].岩土力学,2018,39(S1):529‑536. ZHU Ning, ZHOU Yang, LIU Wei, et al. Study on the influence of diaphragm wall construction on stratum disturbance in Suzhou silt land [J]. Rock and Soil Mechanics, 2018, 39(S1): 529-536. [7] LIU W, SHI P X, CAI G Q, et al. Seepage on local stability of slurry trench in deep excavation of diaphragm wall construction[J]. Computers and Geotechnics, 2021, 129: 103878. [8] QIN C B. Determination of slurry density required for stability of slurry-supported trenches excavated in partially submerged soils[J]. Computers and Geotechnics, 2019, 116: 103212. [9] LEI G H, SUN H S, NG C W W. An approximate analytical solution for calculating ground surface settlements due to diaphragm walling[J]. Computers and Geotechnics, 2014, 61: 108-115. [10] 徐永刚, 魏子龙, 周冠南, 等. 地下连续墙成槽施工参数对槽壁稳定的影响研究[J]. 岩石力学与工程学报, 2011, 30(S2): 3464-3470. XU Yonggang, WEI Zilong, ZHOU Guannan, et al. Analysis of stability of slurry trench sides of diaphragm wall based on construction parameters[J]. Chinese Journal of Rock Mechanics and Engineering, 2011, 30(S2): 3464-3470. [11] 欧明喜, 戴志峰, 陈颖辉, 等. 地下连续墙黏性土夹砂层槽壁稳定性分析[J]. 防灾减灾工程学报, 2020, 40(4): 537-542. OU Mingxi, DAI Zhifeng, CHEN Yinghui, et al. Trench stability analysis of diaphragm wall in cohesive soil sandwiched sand[J]. Journal of Disaster Prevention and Mitigation Engineering, 2020, 40(4): 537-542. [12] 夏元友, 裴尧尧, 王震, 等. 地下连续墙施工影响应力重分布的数值模拟[J]. 岩土力学, 2012, 33(11): 3433-3438. XIA Yuanyou, PEI Yaoyao, WANG Zhen, et al. Numerical simulation of stress redistribution during diaphragm wall construction[J]. Rock and Soil Mechanics, 2012, 33(11): 3433-3438. [13] 樊金,王鹰,王贤能.深圳填海区基坑支护技术特点及现状[J].地下空间与工程学报,2015,11(S2):661‑665,725. FAN Jin, WANG Ying, WANG Xianeng. Characteristics and current situation of foundation pit support technology in Shenzhen reclamation area [J]. Chinese Journal of Underground Space and Engineering, 2015, 11(S2): 661-665, 725. [14] 许宏发, 耿汉生, 李朝甫, 等. 破碎岩体注浆加固体强度估计[J]. 岩土工程学报, 2013, 35(11): 2018-2022. XU Hongfa, GENG Hansheng, LI (ChaoZhao)(Fu), et al. Estimating strength of grouting reinforced bodies in broken rock mass[J]. Chinese Journal of Geotechnical Engineering, 2013, 35(11): 2018-2022. [15] LINGS M, NG C, NASH D. The lateral pressure of wet concrete in diaphragm wall panels cast under bentonite[J].Proceedings of the Institution of Civil Engineers‑Geotechnical Engineering,1994,107(3):163‑172.