Abstract

The minimum socket depth for circular pipe pier-bearing platform socket connection can be calculated according to Article C.0.3 in the Specifications for Design of Highway Precast Concrete Bridges (JTG/T 3365 -05—2022 ).In order to enable engineering designers to fully understand and correctly apply the calculation formula in this article,this paper first introduced the main technical features of the typical connection scheme,as well as the structural failure principles and objectives formulated in the specification of the typical connection scheme.Then,it briefly introduced the experimental research content and results of the typical connection scheme and explained the key construction measures and their functions of the typical connection scheme.Finally,the paper compared the minimum socket depth estimation formula in the specification with experimental research.The results indicate that on the premise of meeting the main technical characteristics and construction requirements of the typical connection scheme,the minimum socket depth calculated according to the relevant formulas in the specifications can meet the structural failure principles and objectives of the typical connection scheme and has a certain safety reserve.

Publication Date

2-22-2025

DOI

10.14048/j.issn.1671-2579.2025.01.017

First Page

146

Last Page

152

Submission Date

March 2025

Reference

[1]中交第二公路勘察设计研究院有限公司.公路装配式混凝土桥梁设计规范:JTG/T 3365 -05—2022 [S].北京:人民交通出版社股份有限公司,2022.CCCC Second Highway Consultant Co.,Ltd..Specifications for design of highway precast concrete bridges:JTG/T 3365 -05—2022 [S].Beijing:China Communications Press Co.,Ltd.,2022.
[2]KHALEGHI B,SCHULTZ E,SEGUIRANT S,et al.Accelerated bridge construction in Washington state:From research to practice [J].PCI Journal,2012,57(4):34-49.
[3]OSANAI Y,WATANABE F,OKAMOTO S.Stress transfer mechanism of socket base connections with precast concrete columns [J].Journal of Structural and Construction Engineering,1996,93(3):266-276.
[4]MASHAL M,PALERMO A.Quasi-static cyclic testing of half-scale fully precast bridge substructure system in high seismicity [C]//Towards Integrated Seismic Design.Auckland:NZSEE Conference,2014:1-9.
[5]HARALDSSON O S,JANES T M,EBERHARD M O,et al.Seismic resistance of socket connection between footing and precast column [J].Journal of Bridge Engineering,2013,18(9):910-919.
[6]MOHEBBI A.Development and seismic evaluation of pier systems w/pocket connections,CFRP tendons,and ECC/UHPC columns [R].Reno:Department of Civil and Environmental Engineering,University of Nevada,2017.
[7]徐艳,曾增,葛继平,等.承插式预制拼装桥墩的最小合理承插深度 [J].同济大学学报 (自然科学版 ),2019,47(12):1706 -1711.XU Yan,ZENG Zeng,GE Jiping,et al.Minimum reasonable socket depth of precast pier-footing with socket connection[J].Journal of Tongji University (Natural Science ),2019,47(12):1706 -1711.
[8]孙贵清,王志刚,曾增,等.公路桥装配式桥墩承插式连接的桩基承台研究 [J].桥梁建设,2020,50(3):81-85.SUN Guiqing,WANG Zhigang,ZENG Zeng,et al.Study of socket connection between modular piers and pile caps for highway bridge [J].Bridge Construction,2020,50(3):81-85.
[9]曾增,王志刚,余坚,等.预制桥墩不同承插式连接构造试验研究 [J].结构工程师,2020,36(5):89-94.ZENG Zeng,WANG Zhigang,YU Jian,et al.Testing of precast pier with different socket connection construction[J].Structural Engineers,2020,36(5):89-94.
[10]左光恒,黄遵义,曾玉昆,等.承插式连接离心预制管墩抗震性能试验研究 [J].结构工程师,2020,36(5):95-100.ZUO Guangheng,HUANG Zunyi,ZENG Yukun,et al.Anti-seismic performance testing of centrifugally precast pipe pier with socket connection [J].Structural Engineers,2020,36(5):95-100.
[11]徐艳,童自亮,曾增,等.灌浆料对预制拼装承插式桥墩力学性能的影响 [J].华南理工大学学报 (自然科学版 ),2021,49(5):84-91.XU Yan,TONG Ziliang,ZENG Zeng,et al.Influence of grout on the mechanical performance of prefabricated assembled socket bridge pier [J].Journal of South China University of Technology (Natural Science Edition ),2021,49(5):84-91.
[12]曾增.承插式预制拼装管墩抗震性能研究 [D].上海:同济大学,2020.ZENG Zeng.Study on seismic performance of socket-type precast assembled pipe pier [D].Shanghai:Tongji University,2020.
[13]岳文超.承插式离心管墩与承台连接力学特性研究 [D].上海:上海应用技术大学,2020.YUE Wenchao.Study mechanical properties on the connection between socket-type centrifugal pipe pier and cap[D].Shanghai:Shanghai Institute of Technology,2020.
[14]XU Y,ZENG Z,WANG Z G,et al.Experimental studies of embedment length of precast bridge pier with socket connection to pile cap [J].Engineering Structures,2021,233:111906.
[15]ZENG Z,XU Y,WANG Z G.Experimental 23 study of the axial bearing capacity of prefabricated pier-cap with socket connection [C]//Shanghai:9th Asia-Pacific Young Researchers and Graduates Symposium,2019.
[16]TONG Z L,XU Y,SHIVAHARI S.Longitudinal loading of socket connection with different bottom plate depth [C]// Shanghai:9th Asia-Pacific Young Researchers and Graduates Symposium,2019.
[17]徐艳,曾增,王志强,等.承插式桥墩连接构造及其力学行为的研究进展 [J].土木工程学报,2023,56(1):90-108.XU Yan,ZENG Zeng,WANG Zhiqiang,et al.Review of the state-of-the-art of the configurations and mechanical behaviors of piers with socket connections [J].China Civil Engineering Journal,2023,56(1):90-108.
[18]葛继平,赖路奇,王志刚.改进承插式连接桥墩与承台的承插深度分析 [J].中外公路,2023,43(2):74-79.GE Jiping,LAI Luqi,WANG Zhigang.Analysis of socket depth between bridge pier and cap with improved socket connection [J].Journal of China & Foreign Highway,2023,43(2):74-79.
[19]王志刚,孙贵清,李谦,等.圆形截面钢筋混凝土墩柱的轴压比限值探讨 [J].公路,2021,66(11):132-137.WANG Zhigang,SUN Guiqing,LI Qian,et al.Discussion on limit value of axial compression ratio of reinforced concrete pier with circular section [J].Highway,2021,66(11):132-137.
[20]中交公路规划设计院有限公司.公路钢筋混凝土及预应力混凝土桥涵设计规范:JTG 3362—2018 [S].北京:人民交通出版社股份有限公司,2018.CCCC Highway Consultants Co.,Ltd..Specifications for design of highway reinforced concrete and prestressed concrete bridges and culverts:JTG 3362—2018 [S].Beijing:China Communications Press Co.,Ltd.,2018.
[21]招商局重庆交通科研设计院有限公司.公路桥梁抗震设计规范:JTG/T 2231 -01—2020 [S].北京:人民交通出版社股份有限公司,2020.China Merchants Chongqing Communications Technology Research & Design Institute Co.,Ltd..Specifications for seismic design of highway bridges:JTG/T 2231 -01—2020 [S].Beijing:China Communications Press Co.,Ltd.,2020.
[22]刘朵,李航,熊辉,等.波纹钢管约束承插式拼装桥墩抗震性能研究 [J].中国公路学报,2023,36(6):123-131.LIU Duo,LI Hang,XIONG Hui,et al.Seismic performance of precast socket piers confined with corrugated steel pipe[J].China Journal of Highway and Transport,2023,36(6):123-131.
[23]吴从晓,高鹏瑜,张广海,等.预制装配式混凝土盖梁受力性能分析 [J].中外公路,2023,43(6):208-217.WU Congxiao,GAO Pengyu,ZHANG Guanghai,et al.Study on mechanical performance of prefabricated concrete cap beam [J].Journal of China & Foreign Highway,2023,43(6):208-217.
[24]陈光伟,傅晨曦,曾慈航.承插式连接钢筋混凝土桥墩力学性能研究 [J].公路,2023,68(6):241-247.CHEN Guangwei,FU Chenxi,ZENG Cihang.Study on mechanical properties of reinforced concrete pier with socket connection [J].Highway,2023,68(6):241-247.
[25]李谦,吕文舒.CFRP加固的承插式桥墩抗震性能分析 [J].中外公路,2023,43(5):109-113.LI Qian,LYU Wenshu.Seismic performance analysis of CFRP reinforced socket pier [J].Journal of China & Foreign Highway,2023,43(5):109-113.
[26]孙振杰,周文轩.高架桥预制拼装承台抗震性能数值模拟研究 [J].公路,2021,66(4):90-96.SUN Zhenjie,ZHOU Wenxuan.Numerical simulation and research on seismic performance of elevated prefabricated cushion cap [J].Highway,2021,66(4):90-96.

Share

COinS