Abstract

Large-sized prestressed reinforced concrete box girder makes it easy to produce floor cracks due to construction temperature. In view of the floor cracks of a short tower cable-stayed wide box girder in Nanchong, Sichuan Province at the beginning of construction, a mixed element calculation model was established to simulate the stress calculation of the effects of temperature difference of hydration heat, sunshine temperature difference, overall cooling, and their combination factors on the floor of 7# section box girder. The stresses in some areas of the floor under the combined conditions of Ⅰ, Ⅳ, and Ⅴ reached 2.0, 4.0, and 4.9 MPa, respectively, which were greater than the allowable value of crack resistance and were consistent with the actual crack situation. Combined with the stress analysis, the subsequent box girder construction adopted the double mixing technology to reduce the hydration heat, extend the final setting time to 16 h, lower the concrete mold temperature, and improve “inner drop and outer protection” maintenance and other measures, so as to effectively control the floor cracks.

Publication Date

6-18-2022

DOI

10.14048/j.issn.1671-2579.2022.03.0024

First Page

131

Last Page

135

Submission Date

May 2025

Reference

[1] 丁勇,赵启林,马方圆,等.普通钢筋混凝土箱梁桥腹板竖向裂缝成因分析[J].工业建筑,2009,39(s1):918-922. Ding Yong, Zhao Qilin, Ma Fangyuan, et al. Causes of vertical cracks in webs of ordinary reinforced concrete box girder bridges [J]. Industrial Construction, 2009, 39(s1): 918-922. [2] 王建强, 吕忠达, 赵卓, 等. 预应力混凝土连续箱梁顶板早期裂缝控制研究[J]. 铁道工程学报, 2019, 36(9): 43-48. WANG Jianqiang, LYU Zhongda, ZHAO Zhuo, et al. Control of the early cracks in the top slab of the prestressed concrete continuous box girder[J]. Journal of Railway Engineering Society, 2019, 36(9): 43-48. [3] 王一霏, 梁伟. 中央索面宽幅五箱室矮塔斜拉桥施工期腹板斜裂缝成因分析[J]. 公路, 2020, 65(11): 194-198. Wang Yifei, Liang Wei. Cause analysis of inclined cracks in webs during construction of extrawide five-cell box-girder extradosed bridge with central cable planes [J]. Highway, 2020, 65(11): 194-198. [4] 常建国. 桥梁工程中预应力钢筋混凝土箱梁预制施工质量控制[J]. 山西建筑, 2019, 45(15): 113-114. CHANG Jianguo. Quality control of prestressed reinforced concrete box girder precast construction in bridge construction[J]. Shanxi Architecture, 2019, 45(15): 113-114. [5] 韦锋, 杨洋, 苏成, 等. 华南地区混凝土刚构桥典型病害调查及分析[J]. 中外公路, 2018, 38(1): 95-98. WEI Feng, YANG Yang, SU Cheng, et al. Investigation and analysis on typical defects of concrete rigid-frame bridges in South China[J]. Journal of China & Foreign Highway, 2018, 38(1): 95-98. [6] 毛建平, 唐赓, 蒙方成, 等. 预应力混凝土连续桁梁刚构桥裂缝分析及加固[J]. 中外公路, 2020, 40(3): 168-173. Mao Jianping, Tang Geng, Meng Fangcheng, et al. Crack analysis and reinforcement of prestressed concrete continuous truss-rigid frame bridge[J]. Journal of China & Foreign Highway, 2020, 40(3): 168-173. [7] 阎培渝, 郑峰. 水泥水化反应与混凝土自收缩的动力学模型[J]. 铁道科学与工程学报, 2006, 3(1): 56-59. YAN Peiyu, ZHENG Feng. Dynamic models of hydration reaction of Portland cement and autogenous shrinkage of concrete[J]. Journal of Railway Science and Engineering, 2006, 3(1): 56-59. [8] 高小建, 巴恒静, 马保国. 混凝土早期自收缩、强度与水泥水化率的关系[J]. 工业建筑, 2006, 36(2): 64-67. GAO Xiaojian, BA Hengjing, MA Baoguo. The relationship among cement hydration degree, compressive strength and autogenous shrinkage of concrete at early ages[J]. Industrial Construction, 2006, 36(2): 64-67. [9] 宋冰泉.津滨轻轨预应力连续箱梁混凝土水化热温度试验[J].铁路标准设计,2003,47(6):24. Song Bingquan. Hydration heat temperature test of prestressed concrete continuous box girder for tianjin binhai light rail [J]. Railway Standard Design, 2003, 47(6): 24. [10] 唐国栋,季文玉,卢文良.预应力混凝土箱形梁水化热试验分析[J].铁道建筑,2004,34(2):78-80. Tang Guodong, Ji Wenyu, Lu Wenliang. Experimental analysis of hydration heat in prestressed concrete box girders [J]. Railway Engineering, 2004, 34(2): 78-80.

Share

COinS