Abstract

In order to study the reasonable completion state of Fenghuang Road Bridge and analyze the construction stage, the finite element model was first established by Midas/Civil, and the correlation matrix was extracted. The minimum strain energy of Fenghuang Road Bridge was used as the objective function, and the mathematical optimization model was established by Matlab to determine the reasonable completion state and construction sequence of the bridge. To ensure reasonable cable force of the bridge, the construction cable force was solved by the forward assembly iteration, and the law of the construction cable force was basically the same as that of the bridge cable force. The model met the requirements of the specification according to the design and calculation.

Publication Date

3-17-2023

DOI

10.14048/j.issn.1671-2579.2023.01.025

First Page

144

Last Page

148