Abstract

During the construction of long-span steel truss suspension bridges,the main girder can be connected in segment-by-segment articulated connection method and rigid-articulated connection combination method.Taking a Yangtze River Highway Bridge in Hubei Province as an example,this paper established the plane calculation model of the full bridge using the Bridge Design and Construction Monitoring System BDCMS to simulate the above two connection methods of the main girder in construction.From the comprehensive analysis of chord member internal forces and line shape of the stiffening beam,this paper finds that the rigid-articulated connection combination method is more appropriate in the construction.In addition,this paper researched the opening width of the temporary hinge through simulation calculation to obtain the optimal conversion time of articulated and rigid connections.

Publication Date

10-28-2024

DOI

10.14048/j.issn.1671-2579.2024.05.015

First Page

143

Last Page

148

Submission Date

February 2025

Reference

[1]王忠彬 ,沈锐利 ,唐茂林 .悬索桥钢桁架加劲梁施工方法分析 [J].石家庄铁道学院学报 ,2006 ,19(1):117-121.WANG Zhongbin ,SHEN Ruili ,TANG Maolin .Construction methods analysis of the steel truss stiffening girder of suspension bridge [J].Journal of Shijiazhuang Railway Institute ,2006 ,19(1):117-121.
[2]谭永高 .大跨径悬索桥桁架加劲梁节段的安装研究 [J].公路 ,2007 ,52(7):46-50.TAN Yonggao .Research on truss stiffening girder segment assembling of long span suspension bridge [J].Highway ,2007 ,52(7):46-50.
[3]连飞飞 .钢桁架悬索桥静力分析及加劲梁吊装方案研究[D].大连 :大连理工大学 ,2013 .LIAN Feifei .Static analysis of steel truss suspension bridge and study on hoisting scheme of stiffening beam[D].Dalian : Dalian University of Technology ,2013 .
[4]张海顺 .大跨度钢桁梁悬索桥临时连接方式分析研究[J].土木工程学报 ,2020 ,53(12): 98-105.ZHANG Haishun .Analysis on temporary connection mode of the large-span steel truss girder suspension bridge[J].China Civil Engineering Journal ,2020 ,53(12): 98-105.
[5]朱红明 ,程海潜 ,李清 ,等.大节段钢桁梁悬索桥主梁架设的窗口铰接法研究 [J].中外公路 ,2021 ,41(6): 120-123.ZHU Hongming ,CHENG Haiqian ,LI Qing ,et al .Window hinged method for erecting main girder of long-span steel truss suspension bridge [J].Journal of China & Foreign Highway ,2021 ,41(6): 120-123.
[6]杨胜 ,樊小伟 .山区钢桁架悬索桥设计与施工 [J].中外公路,2021 ,41(6): 141-144.YANG Sheng ,FAN Xiaowei .Design and constructions of steel truss suspension bridge in mountainous area [J].Journal of China & Foreign Highway ,2021 ,41(6): 141-144.
[7]潘永仁 ,范立础 .大跨度悬索桥加劲梁架设过程的倒拆分析方法 [J].同济大学学报 (自然科学版 ),2001 ,29(5): 510-514.PAN Yongren ,FAN Lichu .Backward analysis method of long-span suspension bridges for erection of stiffening girders [J].Journal of Tongji University ,2001 ,29(5): 510-514.
[8]袁理 ,黄影 ,赵宇清 .悬索桥浅滩区钢桁梁吊装施工新技术[J].中外公路 ,2019 ,39(3): 155-157.YUAN Li ,HUANG Ying ,ZHAO Yuqing .New construction method for hoisting steel truss girders in shoal area of suspension bridges [J].Journal of China & Foreign Highway ,2019 ,39(3):155-157.
[9]刘吉晗 .大跨度铁路悬索桥加劲梁施工方法研究 [D].成都: 西南交通大学 ,2013 .LIU Jihan .Study on construction method of stiffening beam of long-span railway suspension bridge [D].Chengdu : Southwest Jiaotong University ,2013 .
[10]朱立山 ,才振山 ,蒋雨骎 .洞庭湖大桥两跨连续钢桁架加劲梁合龙方案研究 [J].中外公路 ,2019 ,39(5): 118-122.ZHU Lishan ,CAI Zhenshan ,JIANG Yuqin .Closure scheme of stiffening girder for two-span continuous steel truss of Dongting Lake Bridge [J].Journal of China & Foreign Highway ,2019,39(5): 118-122.

Share

COinS