Abstract

To clarify the influence of the cable hoisting system as an auxiliary system on structural stability during the construction of a cantilever casting arch bridge, this paper took the Shuiluo River Bridge as the engineering background, and established the model of the cable-stayed buckle hanging system and the cable hoisting system with the use of finite element software. It analyzed the influence on stability from the different lifting weights in the cable hoisting system, geometric nonlinearity considering geometric initial defects, material nonlinearity, the wall thickness of the buckle tower steel pipe, the removal sequence of buckle anchor cables, the installation number of arch spacer plates of the separated arch bridge, and the lateral movement of the cable lifting weight. The results show the followings. ① For the first type of stability problem, the influence of the cable hoisting system on the stability of the overall structure is mainly concentrated in the early stage of the whole construction process. In the later stage of construction, the stability coefficient trends under the five load conditions tend to be consistent. As the lifting weight of the cable hoisting system increases step by step, the variation pattern of the structural stability coefficient changes accordingly. After a certain lifting weight is reached, the variation pattern of the stability coefficient does not change;② After the cable hoisting load is included, the second type of stability coefficient of the structure further decreases, compared with that of the model without considering the cable hoisting system, which indicates that its influence on structural stability further increases;③ The wall thickness of the buckle tower steel pipe has a much greater influence on material nonlinearity stability than on geometric nonlinearity stability, while the cable hoisting system only influences the value of the stability coefficient and does not influence its variation trend;④ The removal sequence of buckle anchor cables only influences the stability of the cable removal process, while the installation number of arch spacer plates influences the stability of the bare arch after the removal of all buckle anchor cables;⑤ The lateral movement of the lifting weight of the main hoisting system during construction can meet structural safety requirements.

Publication Date

10-29-2026

DOI

10.14048/j.issn.1671-2579.2026.05.015

First Page

145

Last Page

155

Submission Date

October 2026

Reference

[1]胡大琳,陈定市,赵小由,等.大跨径钢筋混凝土拱桥悬臂浇筑施工控制 [J].交通运输工程学报,2016,16(1):25-36.Hu Dalin,Chen Dingshi,Zhao Xiaoyou,et al.Construction control of cantilever casting of long span reinforced concrete arch bridge [J].Journal of Traffic and Transportation Engineering,2016,16(1):25-36.

[2]徐自然,程丽娟,刘榕,等.洞庭溪沅水特大桥缆索及锚固系统设计 [J/OL ].中外公路,2025 -10-20.https://link.cnki.net/urlid/ 43.1363.U.20251017.1121.007.Xu Ziran,Cheng Lijuan,Liu Rong,et al.Design of cable and anchorage system of Dongtingxi river Yuanshui bridge[J/OL ].Journal of China & Foreign Highway,2025 -10-20.https://link.cnki.net/urlid/ 43.1363.U.20251017.1121.007.

[3]谢肖礼,付元杰,邓年春.700 m级中承式缆拱桥设计[J].西南交通大学学报,2019,54(6):1162 -1168,1176.Xie Xiaoli,Fu Yuanjie,Deng Nianchun.Design of half-through cable-arch bridge with 700 m main span [J].Journal of Southwest Jiaotong University,2019,54(6):1162 -1168,1176.

[4]董锐,陈亚钊,郑穆然,等.带L形横撑的大跨 CFST桁式拱桥稳定性分析 [J].土木工程学报,2020,53(5):89-99,128.Dong Rui,Chen Yazhao,Zheng Muran,et al.Stability analysis of long-span CFST truss arch bridges with L-shaped bracings [J].China Civil Engineering Journal,2020,53(5):89-99,128.

[5]黄绍结,李莘哲.红水河特大斜拉桥中跨钢主梁缆索吊装施工关键技术 [J].中外公路,2017,37(3):152-156.Huang Shaojie,Li Xinzhe.Key technology of cable hoisting construction for mid-span steel girder of hongshuihe extra-large cable-stayed bridge [J].Journal of China & Foreign Highway,2017,37(3):152-156.

[6]周水兴,周琳淇,刘彬.斜拉扣挂悬臂浇筑拱桥扣索力与锚索力确定方法研究 [J].桥梁建设,2024,54(5):140-147.Zhou Shuixing,Zhou Linqi,Liu Bin.Research on methods to calculate forces of forestay and backstay cables of cable-stayed cantilever casting system in arch bridge construction [J].Bridge Construction,2024,54(5):140-147.

[7]Wu Y L,Qiu M W,Ma S K,et al.Research on hanger force and main arch stability of long-span concrete-filled steel tube arch bridge [J].Geofluids,2022,2022:3541528.

[8]Tong J S,Lin Z Y,Zhou Q.Local stability of concrete arch bridge based on Ritz method [J].Journal of Computational Methods in Sciences and Engineering,2022,22(1):279-294.

[9]柴生波,杨清华,王秀兰,等.大跨径中承式钢箱系杆拱桥施工阶段稳定性分析 [J].科学技术与工程,2022,22(18):8095 -8102.Chai Shengbo,Yang Qinghua,Wang Xiulan,et al.Stability analysis of long-span half-through steel box tied arch bridge during construction [J].Science Technology and Engineering,2022,22(18):8095 -8102.

[10]田仲初,陈俊岐,戴业,等.悬浇拱桥拱柱同步施工结构力学性能及稳定性研究 [J].世界桥梁,2025,53(3):40-47.Tian Zhongchu,Chen Junqi,Dai Ye,et al.Research on mechanical property and stability of arch bridge constructed by cable-stayed cantilever casting method and parallel construction of arch and spandrel columns [J].World Bridges,2025,53(3):40-47.

[11]施洲,张晓珂.大跨径拱桥缆索施工支架非线性受力特性分析 [J].铁道标准设计,2018,62(2):106-110.Shi Zhou,Zhang Xiaoke.Nonlinear analysis of cable support for long span concrete filled steel tubular arch bridge [J].Railway Standard Design,2018,62(2):106-110.

[12]徐峰,宋军玺,张峰,等.缆索吊装系统索力误差分析 [J].中外公路,2023,43(6):159-164.Xu Feng,Song Junxi,Zhang Feng,et al.Analysis of cable force error of cable installation system [J].Journal of China & Foreign Highway,2023,43(6):159-164.

[13]毛勇,单彧诗,黄侨,等.大跨径缆索承重桥梁静力稳定性分析方法探讨 [J].中外公路,2020,40(2):115-118.Mao Yong,Shan Yushi,Huang Qiao,et al.Discussion on static stability analysis method for long-span cable-supported bridges [J].Journal of China & Foreign Highway,2020,40(2):115-118.

[14]曹锋,郑明杰,马鹏,等.多跨加劲梁悬索桥非线性静风稳定性分析 [J].中外公路,2022,42(4):87-92.Cao Feng,Zheng Mingjie,Ma Peng,et al.Stability analysis of nonlinear static wind on multi-span stiffened girder suspension bridge [J].Journal of China & Foreign Highway,2022,42(4):87-92.

[15]陈铭,万田保,王波.空间缆悬索桥主梁吊装过程分析[J].世界桥梁,2025,53(3):96-101.Chen Ming,Wan Tianbao,Wang Bo.Analysis of stiffening girder hoisting process of suspension bridge with spatially-configured main cables [J].World Bridges,2025,53(3):96-101.

[16]周水兴,孙峰,段佳旺.长阳天池口清江特大桥主拱圈悬臂浇筑斜拉扣挂系统设计 [J].世界桥梁,2024,52(3):61-67.Zhou Shuixing,Sun Feng,Duan Jiawang.Design of cable-stayed cantilever casting system for arch of Tianchikou Qingjiang River bridge in Changyang county [J].World Bridges,2024,52(3):61-67.

[17]彭文韬,刘峰.基于非线性稳定理论的大跨钢箱形提篮拱桥结构分析研究 [J].中外公路,2019,39(2):94-97.Peng Wentao,Liu Feng.Analysis on long span steel box arch bridge structure based on nonlinear stability theory[J].Journal of China & Foreign Highway,2019,39(2):94-97.

[18]孙九春,曹虹.斜拉扣挂缆索吊装系统全过程仿真分析研究 [J].结构工程师,2019,35(3):127-134.Sun Jiuchun,Cao Hong.Analysis of cable-stayed suspension system basic on refinement numerical simulation [J].Structural Engineers,2019,35(3):127-134.

[19]郭增伟,程皓,周水兴.钢管混凝土劲性骨架拱桥混凝土外包过程非线性屈曲分析 [J].重庆交通大学学报 (自然科学版 ),2021,40(10):52-62.Guo Zengwei,Cheng Hao,Zhou Shuixing.Nonlinear buckling analysis of concrete encasement process of arch bridge with CFST stiff skeleton [J].Journal of Chongqing Jiaotong University (Natural Sciences ),2021,40(10):52-62.

[20]邓雪涛,曾德荣,周燕其.大跨度拱桥缆索吊装系统的稳定性有限元分析 [J].重庆交通大学学报 (自然科学版 ),2007,26(增刊 1):3-7.Deng Xuetao,Zeng Derong,Zhou Yanqi.Finite element analysis of stability of cable-hoisting erection system of long-span arch bridge [J].Journal of Chongqing Jiaotong University (Natural Science ),2007,26(S1):3-7.

[21]曾晴晴.缆索吊装混凝土拱桥施工过程的稳定性分析[D].重庆:重庆交通大学,2014.Zeng Qingqing.Analysis on the stability of concrete arch bridge during cable-hoisting construction process [D].Chongqing:Chongqing Jiaotong University,2014.

[22]李旺.大跨箱型拱桥缆索系统受力及单肋合龙稳定性分析[D].长沙:长沙理工大学,2016.Li Wang.Long span arch bridge cable system together by force and the single rib long stability analysis [D].Changsha:Changsha University of Science & Technology,2016.

[23]韩春.缆索吊装施工中塔架稳定性影响因素分析 [D].西安:长安大学,2016.Han Chun.Stability analysis of the scaffold with cableway erection [D].Xi’an:Chang’an University,2016.[24]严小丽.极端气候条件下钢筋混凝土拱桥缆索吊装系统稳定性研究 [D].重庆:重庆交通大学,2017.Yan Xiaoli.The stability of cable-hoisting system research of reinforced concrete arch bridge under extreme weather conditions [D].Chongqing:Chongqing Jiaotong University,2017.

[25]王涛.大跨度钢筋混凝土拱桥斜拉扣挂施工稳定性分析研究 [D].贵阳:贵州大学,2018.Wang Tao.Stability analysis of cable-stayed suspension construction of long-span reinforced concrete arch bridge[D].Guiyang:Guizhou University,2018.

[26]唐博文.沙坨特大拱桥悬臂浇筑施工稳定性研究 [D].长沙:长沙理工大学,2020.Tang Bowen.Research on stability of cantilever casting construction of Shatuo extra large arch bridge [D].Changsha:Changsha University of Science & Technology,2020.

[27]赵攀攀.基于 Midas/Civil 的钢管混凝土拱桥双非线性稳定性分析 [D].石家庄:石家庄铁道大学,2021.Zhao Panpan.Bi-linear stability analysis of CFST arch bridge based on Midas/Civil [D].Shijiazhuang:Shijiazhuan g Tiedao University,2021.

Share

COinS