Abstract

To address the engineering challenge of excessive structural settlement caused by shield tunneling at close range beneath existing pile-supported buildings, this paper takes an intercity railway shield tunnel project passing beneath an industrial park as its engineering background. Numerical simulations were conducted using GTS NX software and combined with monitoring data collected during shield tunneling to investigate the effects of pile cutting by the shield machine on the ground surface and buildings, as well as to examine the rationality of reinforcement measures and the mechanisms of pile foundation deformation. The results are as follows. ① The ground surface exhibits a slight heaving trend, while the building settlement is significantly greater than the ground surface settlement. The stage where the shield cuts through the piles contributes to over 65% of the total settlement, representing the primary risk source. The secondary disturbance effect caused by the overlapping excavation of twin tunnels increases the pile foundation settlement by approximately 40% compared with the single-tunnel condition, resulting in a maximum building settlement of ‒ 21.66 mm;② The combined reinforcement method of ground grouting and raft foundation underpinning is effective in controlling structural displacement, reducing pile foundation settlement by an average of 5.2‒6.1 mm (a reduction of 35%‒40%) and successfully keeping settlement at most monitoring points within the allowable range;③ Pile foundations intruding into the tunnel with a clearance of less than 0.5D exhibit the most severe deformation. The stiffness effect of the superstructure leads to “coordinated deformation of pile groups ”, which inhibits differential settlement but exacerbates overall settlement. The findings can provide a reference for risk control and reinforcement design of shield tunnels passing underneath existing pile-supported buildings with masonry structures.

Publication Date

10-29-2026

DOI

10.14048/j.issn.1671-2579.2026.05.024

First Page

230

Last Page

237

Submission Date

October 2026

Reference

[1]万波.大直径泥水盾构隧道施工现状及重难点思考与讨论[J].广东土木与建筑,2022 (6):92-99.Wan Bo.Thinking and discussion on the construction of large-diameter mud-water shield tunnel [J].Guangdong Architecture Civil Engineering,2022 (6):92-99.

[2]苏秀婷,陈健,李明宇,等.大直径泥水盾构隧道穿越复杂环境地层变形敏感性研究 [J].工程地质学报,2021,29(5):1587 -1598.Su Xiuting,Chen Jian,Li Mingyu,et al.Sensitivity analysis of deformation of large diameter mudwater shield through complex environment [J].Journal of Engineering Geology,2021,29(5):1587 -1598.

[3]卢鑫月,许成顺,侯本伟,等.基于动态贝叶斯网络的地铁隧道施工风险评估 [J].岩土工程学报,2022,44(3):492-501.Lu Xinyue,Xu Chengshun,Hou Benwei,et al.Risk assessment of metro construction based on dynamic Bayesian network [J].Chinese Journal of Geotechnical Engineering,2022,44(3):492-501.

[4]潘涛.软土地区双线区间盾构隧道施工对周边地表以及建筑物沉降的影响 [J].水文地质工程地质,2022,49(1):101-108.Pan Tao.Influences of double-track shield tunnel construction on settlements of adjacent ground and buildings in a soft soil area[J].Hydrogeology & Engineering Geology,2022,49(1):101-108.

[5]宋伟涛,张佩,杜修力,等.土性对浅埋盾构隧道施工地层响应影响研究 [J].岩土力学,2025,46(7):2179 -2188.Song Weitao,Zhang Pei,Du Xiuli,et al.Influence of soil property on ground response during construction of shallow shield tunnel [J].Rock and Soil Mechanics,2025,46(7):2179 -2188.

[6]张心悦,张晓平,许丹,等.气压辅助土压平衡盾构掘进地左线表变形规律研究 [J].工程地质学报,2025,33(1):292-301.Zhang Xinyue,Zhang Xiaoping,Xu Dan,et al.Study on the surface deformation law of shield tunneling in air pressure assisted earth pressure balance mode [J].Journal of Engineering Geology,2025,33(1):292-301.

[7]叶飞,杨永,李思翰,等.曲线段盾构隧道施工期管片错台发展规律研究 [J].铁道标准设计,2026,70(6):126-134.Ye Fei,Yang Yong,Li Sihan,et al.Study on the development law of segments misalignment during the construction period of curved shield tunnel [J].Railway Standard Design,2026,70(6):126-134.

[8]刘凤洲,徐前卫,种记鑫,等.含闪长岩地层盾构开挖面失稳判定及施工监测分析 [J].岩土工程学报,2023,45(11):2327 -2335.Liu Fengzhou,Xu Qianwei,Zhong Jixin,et al.Instability determination and construction monitoring analysis of shield excavation face in diorite-bearing strata [J].Chinese Journal of Geotechnical Engineering,2023,45(11):2327 -2335.

[9]闫邵航,王剑宏,杜昌言,等.超大直径盾构隧道穿越地上水库堤坝沉降变形试验研究 [J].土木工程学报,2024,57(增刊 2):73-79.Yan Shaohang,Wang Jianhong,Du Changyan,et al.Experimental study on settlement and deformation caused by extra-large diameter shield tunneling through above-ground reservoir embankment [J].China Civil Engineering Journal,2024,57(S2):73-79.

[10]罗旭,张召峰,傅鹤林,等.盾构同步注浆参数对地表变形影响研究 [J].中外公路,2025,45(3):172-182.Luo Xu,Zhang Zhaofeng,Fu Helin,et al.Research on influence of shield synchronous grouting parameters on surface deformation [J].Journal of China & Foreign Highway,2025,45(3):172-182.

[11]Zhang C R,Zhao Y J,Zhang Z,et al.Case study of underground shield tunnels in interchange piles foundation underpinning construction [J].Applied Sciences,2021,11(4):1611.

[12]Tian Z X,Zhang Z Y,Zhang G Z,et al.Impact analysis of tunnel crossing pile foundation at different angles [J].Scientific Reports,2025,15:4770.

[13]林向阳,高伟琪,刘学彦,等.盾构直接切削大直径桩施工技术研究 [J].土木工程学报,2024,57(增刊 1):178-183.Lin Xiangyang,Gao Weiqi,Liu Xueyan,et al.Research on the construction technology of directly cutting large-diameter piles with shield tunneling [J].China Civil Engineering Journal,2024,57(S1):178-183.

[14]马永政,郑义,朱瑶宏,等.机械法联络通道施工参数全局敏感性影响分析 [J].隧道建设 (中英文 ),2025,45(1):98-108.Ma Yongzheng,Zheng Yi,Zhu Yaohong,et al.Analysis of global sensitivity of construction parameters in mechanized cross-passage excavation [J].Tunnel Construction,2025,45(1):98-108.

[15]雷华阳,刘濠瑜,许英刚.盾构施工诱发的筏板基础建筑沉降影响分区研究 [J].地下空间与工程学报,2025,21(1):312-319.Lei Huayang,Liu Haoyu,Xu Yinggang.Study on the settlement affected zones of raft foundation buildings induced by shield construction [J].Chinese Journal of Underground Space and Engineering,2025,21(1):312-319.

[16]王鹏飞,邹利,乙珂豪,等.考虑双线掘进和建筑结构耦合作用时地铁盾构下穿建筑物施工的地面沉降规律 [J].城市轨道交通研究,2025,28(4):145-150.Wang Pengfei,Zou Li,Yi Kehao,et al.Land subsidence law of subway shield tunnel construction under-crossing buildings considering the coupling effect of double-line tunneling and building structure [J].Urban Mass Transit,2025,28(4):145-150.

[17]苏恒,王士民,朱旭红,等.考虑空间效应的盾构刀具切削桩基主筋力学特征研究 [J].现代隧道技术,2025,62(3):139-150.Su Heng,Wang Shimin,Zhu Xuhong,et al.Study on the mechanical characteristics of shield cutter cutting pile foundation main reinforcement considering spatial effects[J].Modern Tunnelling Technology,2025,62(3):139-150.

[18]张建华,王宏伟,陈培新,等.杭州地铁 4号线盾构下穿电力隧道直接切桩沉降分析 [J].工程力学,2022,39(增刊1):144-152.Zhang Jianhua,Wang Hongwei,Chen Peixin,et al.Surface settlement analysis of shield passing through power tunnel and directly cutting pile foundation of Hangzhou metro line 4[J].Engineering Mechanics,2022,39(S1):144-152.

[19]Zhu X,Ma S J,Hong K R,et al.Effects on upper masonry structures caused by double-line parallel shield cutting group pile construction [J].Scientific Reports,2024,14:22379.

[20]Su J,Pan Y Q,Niu X K,et al.Effect of shield tunneling on adjacent pile foundations in water-rich strata [J].Transportation Geotechnics,2025,52:101557.

[21]鲁立洋,刘欢,李聘聘.强风化层超浅埋隧道高压旋喷桩荷载试验研究 [J].中外公路,2023,43(1):155-161.Lu Liyang,Liu Huan,Li Pinpin.Experiment research of high pressure jet grouting pile on ultra-shallow buried tunnel in strong weathered stratum [J].Journal of China & Foreign Highway,2023,43(1):155-161.

[22]黄跃廷,王崇华,汪慧,等.隧道全断面超前注浆对地层扰动特性研究 [J].中外公路,2023,43(6):273-277.Huang Yueting,Wang Chonghua,Wang Hui,et al.Study on disturbance characteristics of ground in full-section tunnel under advance grouting [J].Journal of China & Foreign Highway,2023,43(6):273-277.

Share

COinS